Unknown-1.png

Current Work

January 28, 2021

The Sossamon Construction crew is making rapid progress installing sidewalks on the east side of Cannon St. Currently approaching the Cannon Centre, the crew expects to complete the sidewalk to Arlington Ave. by next Monday.

Work will then move to the west side of the street and advance south from Arlington Ave. with an anticipated completion date of February 12.

A major task awaiting Sossamon beginning in mid-February is running 42-inch storm drain pipe from Cannon St. (near the boundary of the Parkview Greer project) across to N. Main St.

Greer CPW has completed its gas line installation on Cannon St. One section of sewer line outside the Cannon Centre will be lined with cure-in-place piping  – a one-day job currently planned for late February. Limited electrical work remains as CPW works to complete its utility upgrades on Cannon St.

A binder layer of asphalt has been applied to Cannon St. The top coat will be applied this spring, once the S.C. Department of Transportation allows asphalt paving to resume. Cannon St., Jason St. and N. Main St. (south of Arlington Ave.) are scheduled for repaving.

 

JOIN OUR MAILING LIST

Never miss an update about the CenterG Project taking place in Downtown Greer. Receive news via email before it is posted. You'll also have a chance to win some swag!